Matakauri Lodge is an alpine lakeside retreat nestled in one of the world's most serenely beautiful landscapes. Spectacularly situated on Lake Wakatipu and only seven minutes from Queenstown, this project involved constructing a complicated and highly specified 465m2 luxury lodge, on an extremely tight site.

The project required an accelerated construction programme of 7.5 months over winter so it could be open in time for the peak summer season.

The challenges involved managing the tight time constraints, building throughout the winter months and working around an operational 6-star lodge. All the while ensuring the highest quality of finish and that the completion date was achieved.

We developed a strategy to reduce the project programme risk relating to snowfall and adverse weather by creating a shrink-wrapped temporary structure over the entire project.

The project was completed on time and under budget while exceeding the Clients extremely high quality expectations.

PROJECT

Matakauri Lodge Owners Cottage

TYPE

Commercial,Residential

CLIENT

Matakauri Lodge

LOCATION

Queenstown

STARTED

April, 2013

COMPLETED

November, 2013

BUDGET

$3,500,000

Other Projects

Woodend School

Woodend School

Brosnan Construction were awarded the contract to construct an 800 square metres 2 storey redevelopment in the growing North Canterbury township of Woodend. The scope for Woodend School included a new two storey eight classroom block. In addition to this, there are some minor weather-tightness repairs for the three remaining buildings. At the completion of the project, the demolition of a two classroom cebus unit will be completed.

Read More

Reefton Area School

Reefton Area School

Refurbishments to school premises always have attendant challenges, due in the main to tight deadlines and the need for the school to continue with its vital role of education whilst the project continues. Add-in a location where high winds are prevalent and that makes for a tough project.

Read More

McTiegues Road Stage 5

McTiegues Road Stage 5

The key to this project was the way in which Brosnan Construction worked with their associated trades and supply chain during a short timescale to ensure delivery of this phase of the construction.

Read More

Kidicorp - New Build Child Care Centre

Kidicorp - New Build Child Care Centre

Delays sometimes seem to be the byword of construction, but when they are caused by building consent issues, they can put great pressure on the construction team when the finish date is fixed and immovable. Such was the case with this important project in Papakura...