Projects

What We Do

University of Canterbury Locke & Logie Buildings

These buildings are of 1960’s design, constructed in in-situ concrete column, beam and ifloor with precast concrete façade envelope. The refurbishment is driven by the need to upgrade the buildings to more efficient electrical and mechanical systems. Minor internal layout changes will be completed prior to the installation of new ceilings, wall linings and floor coverings. New kitchenettes will also be installed to collaborative shared spaces for teaching faculties. Externally, works will be limited to new window joinery to all elevations.

Brosnan has previously completed an upgrade to the toilet blocks of the Locke and Logie buildings and we identified the need to manage the student pedestrian movements to the external carriageways. Further, the need was identified to maintain access to the existing ablutions facilities and the lift well lobby, a view supported by the University.

The delivery of this project requires two stages. Stage 1 will focus on completion of the Logie building with a short period for decant and building re-occupancy prior to works commencing on Stage 2—the Locke building.

This staged approach will allow the different trade tasks to be separated into three teams: Disconnections/demo and wall framing; followed by first fix, drywall and stopping; and finally, second fix and finishing trades.

An initiative in this project was to provide material and worker distribution by way of a goods lift to the linkway between the two buildings. This location will enable the lift to be utilised during both stages of delivery. The planned location also mitigates any significant impact on pedestrian movements of students.

Working within the University environment comes with many challenges in minimising disruption to existing departments, maintaining pedestrian accessways and ensuring trade behaviours are in line with University protocols. Further, our site is adjacent to the main disabled car parking spaces for campus which are to remain accessible at all times irrespective of an anticipated heavy delivery schedule.

PROJECT

University of Canterbury Locke & Logie Buildings

TYPE

Education

CLIENT

University of Canterbury

LOCATION

Christchurch

STARTED

February, 2019

COMPLETED

December, 2019

BUDGET

$5,700,000

Other Projects

Te Kura Kaupapa Maori o Waitaha

Te Kura Kaupapa Maori o Waitaha

This project was essentially a weather-tightness assignment involving the School’s Main Hall and supporting facilities. What might appear a straightforward project was complicated by a capped budget and the tight deadline to hand the site back to the School on schedule.

Read More

17 London Street, Lyttelton

17 London Street, Lyttelton

Enabling commercial tenants to resume trading in the shortest possible timeframe is a challenge in itself when repairing earthquake damaged premises, but when further damage is only discovered during the project, then it can place strain on both timelines and budget. Dealing with these issues professionally is paramount to success.

Read More

Mon Desir Apartments

Mon Desir Apartments

The ‘leaky home’ issues in New Zealand construction have caused numerous problems for both homeowners and the industry alike. This project typified that situation, with a set of anxious, largely elderly, owners and an initial contractor that went into liquidation during phase one of the project. It was against this backdrop that Brosnan Construction were engaged to complete the contract.

Read More

144 - 146 Lichfield Street

144 - 146 Lichfield Street

Brosnan Construction have worked on numerous projects resulting from the damage caused by the Christchurch earthquakes, however, this one was a bit special. Involving an historic building dating back to the early 1900’s, it was one of few commercial buildings on Lichfield Street to still be repairable.

Read More