Projects

What We Do

University of Canterbury Locke & Logie Buildings

These buildings are of 1960’s design, constructed in in-situ concrete column, beam and ifloor with precast concrete façade envelope. The refurbishment is driven by the need to upgrade the buildings to more efficient electrical and mechanical systems. Minor internal layout changes will be completed prior to the installation of new ceilings, wall linings and floor coverings. New kitchenettes will also be installed to collaborative shared spaces for teaching faculties. Externally, works will be limited to new window joinery to all elevations.

Brosnan has previously completed an upgrade to the toilet blocks of the Locke and Logie buildings and we identified the need to manage the student pedestrian movements to the external carriageways. Further, the need was identified to maintain access to the existing ablutions facilities and the lift well lobby, a view supported by the University.

The delivery of this project requires two stages. Stage 1 will focus on completion of the Logie building with a short period for decant and building re-occupancy prior to works commencing on Stage 2—the Locke building.

This staged approach will allow the different trade tasks to be separated into three teams: Disconnections/demo and wall framing; followed by first fix, drywall and stopping; and finally, second fix and finishing trades.

An initiative in this project was to provide material and worker distribution by way of a goods lift to the linkway between the two buildings. This location will enable the lift to be utilised during both stages of delivery. The planned location also mitigates any significant impact on pedestrian movements of students.

Working within the University environment comes with many challenges in minimising disruption to existing departments, maintaining pedestrian accessways and ensuring trade behaviours are in line with University protocols. Further, our site is adjacent to the main disabled car parking spaces for campus which are to remain accessible at all times irrespective of an anticipated heavy delivery schedule.

PROJECT

University of Canterbury Locke & Logie Buildings

TYPE

Education

CLIENT

University of Canterbury

LOCATION

Christchurch

STARTED

February, 2019

COMPLETED

December, 2019

BUDGET

$5,700,000

Other Projects

The Sails Building

The Sails Building

The earthquakes of 2010 and 2011 left many buildings in Christchurch damaged. Some have had to be demolished, but for The Sails Building on Ferry Road, Brosnan Construction undertook structural repairs and upgrades, through to interior fit-out.

Read More

North Shore Hospital Building 5

North Shore Hospital Building 5

North Shore Hospital Building 5 was constructed in the 1960’s for the purpose of being occupied as staff accommodation. The structure of the building consists of an inadequately filled concrete masonry reinforced exterior cladding with a hollow clay block used as formwork for the 70mm concrete floors. The 2nd story resides of a mix of internal concrete brace walls and structural timber holding the light weight roof. The new purpose of the building is to create a hospital outpatients ward on level zero and offices and teaching facilities on level one and two.

Read More

137 Tamaki Drive

137 Tamaki Drive

This project involves the removal and replacement of the building’s existing balcony cladding, installation of a new gutter system, and repainting the exterior block, plaster, aluminium garage doors, timber pergola and exterior steel beams in accordance with Resene’s specifications. The building comprises four apartments each on its own level, plus occupant garaging on the ground floor.

Read More

McTiegues Road Stage 5

McTiegues Road Stage 5

The key to this project was the way in which Brosnan Construction worked with their associated trades and supply chain during a short timescale to ensure delivery of this phase of the construction.

Read More