Brosnan successfully negotiated the construction of the 14,000 square metre industrial offices and warehouse on Roscommon Road, Wiri and was appointed the project by the Hugh Green Group.

Part of this project included Brosnan managing the design and build of the warehouse’s post-tension floor. The post-tension floor was one of the most important aspects of this project and as a multiple stakeholder project, working with potential tenants as well as our client, it was important for Brosnan to gain a solid understanding of the requirements specific to each party and to provide a solution that would effectively meet the needs of all involved.

During the construction process, an international tenant (Jamestrong Packaging) was secured by HGL and Brosnan was required to manage some significant and complex changes to the project scope. 

This involved preparing budget estimates and programs for the proposed changes from concept drawings and design briefs. We also provided expert advice on material selection, construction details and what the design team needed to focus on in order to minimise the impact of the proposed changes on the completion due date.

We are proud that our strong ability to navigate challenges and offer flexible solutions has met the evolved requirements of the client and tenants and has kept this major project on-track for a timely completion.

PROJECT

Roscommon Road, Wiri

TYPE

Commercial,Industrial

CLIENT

Hugh Green Group

LOCATION

Wiri

STARTED

October, 2017

COMPLETED

January, 2019

BUDGET

$17,200,000

Other Projects

The Sails Building

The Sails Building

The earthquakes of 2010 and 2011 left many buildings in Christchurch damaged. Some have had to be demolished, but for The Sails Building on Ferry Road, Brosnan Construction undertook structural repairs and upgrades, through to interior fit-out.

Read More

137 Tamaki Drive

137 Tamaki Drive

This project involves the removal and replacement of the building’s existing balcony cladding, installation of a new gutter system, and repainting the exterior block, plaster, aluminium garage doors, timber pergola and exterior steel beams in accordance with Resene’s specifications. The building comprises four apartments each on its own level, plus occupant garaging on the ground floor.

Read More

Queenstown Fire Station

Queenstown Fire Station

The upgrade of a working Fire Station is inherently fraught with challenges for the construction team. Brosnan Construction worked closely with the NZ Fire Service to ensure the Station was able to operate at full capacity, whilst achieving a great construction outcome...

Read More

Kaiapoi High School

Kaiapoi High School

Following the successful delivery of a new early learning centre on campus in 2018, Brosnan was re-engaged to construct a new gymnasium and adjacent sports courts for Kaiapoi High School.

Read More