Roscommon Road, Wiri

Brosnan successfully negotiated the construction of the 14,000 square metre industrial offices and warehouse on Roscommon Road, Wiri and was appointed the project by the Hugh Green Group.

Part of this project included Brosnan managing the design and build of the warehouse’s post-tension floor. The post-tension floor was one of the most important aspects of this project and as a multiple stakeholder project, working with potential tenants as well as our client, it was important for Brosnan to gain a solid understanding of the requirements specific to each party and to provide a solution that would effectively meet the needs of all involved.

During the construction process, an international tenant (Jamestrong Packaging) was secured by HGL and Brosnan was required to manage some significant and complex changes to the project scope. 

This involved preparing budget estimates and programs for the proposed changes from concept drawings and design briefs. We also provided expert advice on material selection, construction details and what the design team needed to focus on in order to minimise the impact of the proposed changes on the completion due date.

We are proud that our strong ability to navigate challenges and offer flexible solutions has met the evolved requirements of the client and tenants and has kept this major project on-track for a timely completion.

PROJECT

Roscommon Road, Wiri

TYPE

Commercial

CLIENT

Hugh Green Group

LOCATION

Wiri

STARTED

October, 2017

COMPLETED

January, 2019

BUDGET

$17,200,000

Other Projects

144 - 146 Lichfield Street

144 - 146 Lichfield Street

Brosnan Construction have worked on numerous projects resulting from the damage caused by the Christchurch earthquakes, however, this one was a bit special. Involving an historic building dating back to the early 1900’s, it was one of few commercial buildings on Lichfield Street to still be repairable.

Read More

23 Hargreaves Street

23 Hargreaves Street

This large-scale remediation project involves the refurbishment of 33 apartments at Hargreaves Street in one of Auckland’s premier CBD locations.

Read More

Kidicorp - New Build Child Care Centre

Kidicorp - New Build Child Care Centre

Delays sometimes seem to be the byword of construction, but when they are caused by building consent issues, they can put great pressure on the construction team when the finish date is fixed and immovable. Such was the case with this important project in Papakura...

Read More

Wanaka House

Wanaka House

Building a new home for the owners is always a privilege, but when it’s overlooking the stunning scenery of Lake Wanaka, then it takes on a whole new imperative. Delivering a great place to live was as important as finishing on time and on budget.

Read More