Roscommon Road, Wiri

Brosnan successfully negotiated the construction of the 14,000 square metre industrial offices and warehouse on Roscommon Road, Wiri and was appointed the project by the Hugh Green Group.

Part of this project included Brosnan managing the design and build of the warehouse’s post-tension floor. The post-tension floor was one of the most important aspects of this project and as a multiple stakeholder project, working with potential tenants as well as our client, it was important for Brosnan to gain a solid understanding of the requirements specific to each party and to provide a solution that would effectively meet the needs of all involved.

During the construction process, an international tenant (Jamestrong Packaging) was secured by HGL and Brosnan was required to manage some significant and complex changes to the project scope. 

This involved preparing budget estimates and programs for the proposed changes from concept drawings and design briefs. We also provided expert advice on material selection, construction details and what the design team needed to focus on in order to minimise the impact of the proposed changes on the completion due date.

We are proud that our strong ability to navigate challenges and offer flexible solutions has met the evolved requirements of the client and tenants and has kept this major project on-track for a timely completion.

PROJECT

Roscommon Road, Wiri

TYPE

Commercial

CLIENT

Hugh Green Group

LOCATION

Wiri

STARTED

October, 2017

COMPLETED

January, 2019

BUDGET

$17,200,000

Other Projects

17 London Street, Lyttelton

17 London Street, Lyttelton

Enabling commercial tenants to resume trading in the shortest possible timeframe is a challenge in itself when repairing earthquake damaged premises, but when further damage is only discovered during the project, then it can place strain on both timelines and budget. Dealing with these issues professionally is paramount to success.

Read More

The Sails Building

The Sails Building

The earthquakes of 2010 and 2011 left many buildings in Christchurch damaged. Some have had to be demolished, but for The Sails Building on Ferry Road, Brosnan Construction undertook structural repairs and upgrades, through to interior fit-out.

Read More

Summerset Villas Wigram

Summerset Villas Wigram

The development of a major retirement village on the South-Western outskirts of Christchurch is a major undertaking. Brosnan Construction has initially been awarded the contract to construct the main, three-storey centre for the complex using innovative, new techniques.

Read More

Oak Shores Remediation - Precontract Works

Oak Shores Remediation - Precontract Works

Oak Shores is an apartment remediation project. The scope of works includes remediation of the external cladding, structural elements, balconies, balustrades, externals walls, window joinery, roofs, courtyard, basement walls and addressing passive fire non-compliant works. The ECI team has consisted of key Auckland based managers and the Queenstown delivery team to ensure the client receives the full breadth of Brosnan’s knowledge and capability.

Read More